WAPDA completes Golen Gol-Timergara transmission line
Pakistan Water and Power Development Authority (WAPDA) has succeeded in completing the most difficult transmission line from Golen Gol, Chitral to Timergara for evacuation of power generated by Golen Gol Hydropower Project to the national grid.
Talking to media, WAPDA spokesman said the 180-kilometer long Golen Gol-Timergara transmission line crosses through the most difficult mountainous terrain having extreme weather conditions.
The transmission towers in Pakistan have never been erected earlier at this altitude.
He said Golen Gol Hydropower Project will provide 436 million units of electricity to the National Grid every year.
Benefits of the project have been estimated at 3.7 billion rupees per annum.
Related News
Japan, Pakistan emphasize mutual benefits in key sectors
ISLAMABAD, APR 19 /DNA/ – Director General (Asian Affairs Department) of the Japanese Ministry ofRead More
PM commends UAE’s leadership response to recent rains in telephone call with President Mohamed bin Zayed
ISLAMABAD, APR 19 /DNA/ – Prime Minister of Pakistan Muhammad Shehbaz Sharif held a telephoneRead More
Comments are Closed